Project Designed with DeepEX Software

A 6.5m deep excavation in highwater table conditions was supported by a perimeter secant pile wall with one level of internal bracing. Haris Lamaris and associates used DeepEX to quickly size the deep excavation. The process involved analyzing a 2D section of the excavation first with conventional and nonlinear analysis methods in DeepEX. Then, the internal bracing model was setup with the frame analysis module of DeepEX where the structural design of the framing was performed. Last, the frame model (internal walers and braces) was exported in 3D, virtual reality, and augmented reality with HoloDeepEX. The excavation, constructed by Stylianou construction, has been completed and the resemblance with the 3D virtual reality model is stunning!

Internal bracing for a secant pile excavation in DeepEX

Secant pile deep excavation section

 

Secant pile deep excavation in augmented reality in Cyprus

The project was constructed by Stylianou construction: Stylianou construction cyprus

Avoid a One-Million Dollar Mistake - Try DeepEX

BOOK A FREE WEB PRESENTATION

FULL FEATURES DEMO  - TRY NOW

SIGN UP TO TRY ALL FEATURES, GET ACCESS FOR A FULL TRIAL

 

      Deep Excavation LLC
    240 W 35th Street, Suite 1004
    New York, NY, 10001
    U.S.A