Inclinometer Monitoring Example

Subway Metro Station Excavation - Results Monitored with SiteMaster!

SiteMaster is used to analyze inclinometer data from 33m excavation for a subway station excavation in Europe. The unique capabilities of SiteMaster allowed the presentation of data through a construction timeline that identified issues with obtained results.

SIteMaster allowed the plotting of inclinometer data on plan where maximum displacements, while the contractor was able to apply corrections and plot displacement against construction progress.

polar-inclinometer-plot.jpg

Sample cumulative inclinometer displacements for metro subway station in Europe are displayed below:

metro-station-inclinometer-plot.jpg

Solutions for Geotechnical Engineering Professionals:

Logo_DeepEX.png

DeepEX

Deep
Excavations
Design
Software

Learn More

dfnd.jpg

DeepFND

Pile Foundations
Design
Software

Learn More

HP.jpg

HelixPile

Helical
Piles
Design
Software

Learn More

SP.jpg

SnailPlus

Soil Nail
Walls
Design
Software

Learn More

      Deep Excavation LLC
    240 W 35th Street, Suite 1004
    New York, NY, 10001
    U.S.A