|
Soil conditions in the site were typical of downtown Chicago: 7' of fill, 18'
of fine sand (SP), 30' of soft to tough silty clay (CL), over very tough to
hard clay (CL), and hardpan. The soft clay has undrained shear strength su =
0.4 - 1.0 ksf, increasing with depth.
The tiebacks were inclined from 10.3° to 17° in order
to obtain a grouted zone of 10' to 20' within the sand stratum.
All ties were regroutable with a design capacity of 60 Tons each.
Five tiebacks and two rakers were installed in each slurry wall
panel. The rakers had a design capacity of 225 Tons each, with
one raker placed at a drilled caisson and another placed midway
between caissons.
Out of the 174 ties, 14 did not obtain the design capacity and had to be
regrouted to give acceptable results. All ties were locked off at 60 Tons but
load picked up from 63 Tons to 75 Tons. Tieback loads remained at prestress
levels while the berm was not removed. All tiebacks were cut-off once the
ground-floor slab was in place. The average maximum raker load was 200 Tons,
slightly less than the 225-Tons design capacity. Readings taken at the longest
diagonal strut at the northeast corner showed an axial load varying from 31
Tons to 181 Tons, with a design load of 320 tons. It was believed that soil
arching partly caused the smaller observed load.
Offset surveys indicated that maximum wall movements at the top of the wall
were in the range of 1" to 3". Lateral movements as measured from the
surveys were smaller than inclinometer measurements at the top of the wall.
Inclinometer deflection data is displayed in Figures 5.13 & 5.14
(Gnaedinger et al., 1975). Maximum soil movement as determined by inclinometers
was slightly more than 6", but most were less than 2" throughout the
depth of the inclinometer casing. These large movements at the top the casing
most likely reflect fill sliding under the guidewalls or other surface
construction activities. The bottom of the slurry wall translated by as much as
1.2" towards the excavation, which emphasizes the importance of adequate
embedment into a stiff stratum for controlling such deformations.
Wall movements were more or less observed throughout the wall perimeter. This
indicates that the wall actually spanned across the drilled caissons as
designed. Lateral movements were increasing as the excavation progressed. The
effect of tieback prestressing can be seen in the sharply bent deflection
shapes at the tie elevations. Raker prestress did not seem enough to prevent
the bulging deflections that occurred in most locations. Apparently the raker
prestress level was not high enough to prevent such a condition.
Under 200 tons with a 50-ton prestress the calculated elastic yielding is close
to 0.21" for each raker. This means that the average maximum stress on
each steel pipe was 14 ksi. This calculation was made assuming that the rakers
were under compression only. Apparently the walls deflected much more than the
0.21" at the raker elevation, which suggests that either the base slab
shortened under the raker load or that the rakers actually slipped to
accommodate for the typical 2" observed movements.
Settlement observations were only made at distances greater than 20' to 40'
from the wall. At points within 40' of the wall settlements were in the order
of 1.5" on Pearson, Seneca, and Chestnut Streets, and 0.5" on
Michigan Avenue. On Chestnut and Pearson Streets maximum settlements at 60'
from the excavation were about 1inch. At the same distance the maximum
settlement at Michigan Ave. and Seneca was close to 0.5". At this project
there were little to no movement during caisson construction since the
perimeter caissons were provided with steel liners, and cement grouting was
used to seal the space between the liner and the excavated hole.
|