|
Wall movements were generally small through out the project site, especially in
the northern project side, since most panels deflected less than 0.6". The
majority of these wall panels had maximum deflections around 0.4". In the
southern wall a similar pattern in wall movements was observed. In the eastern
corner of the project wall deflections were the greatest (I-83: Max 1.2",
I-1: Max 0.7").
The slurry wall at panel 83 was embedded basically in clay. This probably
explains the mostly translative and slightly rotational movement of that panel.
Panel 83 in the southeastern corner had a complex construction history but the
final deflections were much smaller than then maximum deflections. Panel 83 and
panels at the east wall (I-1) were supported by braces. Deflections at I-83
decreased when the deflections at I-1 increased and vise versa (for recorded
data after 10-Dec-1981). Apparently stiffening of the local corner bracing was
effective in reducing wall movements in I-83. Some panels showed deep seated
movements (Panel I-24) but non-the less overall movements were generally small.
Some movement could be attributed to mat shrinkage. It is interesting to note
that inclinometers extending beneath the slurry wall showed that wall
deflections at the base of slurry wall were in the order of 0.3" to
0.4". This kind of movement corresponded for close to half of the total
wall deflections in some panels.
Building settlement control was crucial in the northern side of the project.
Building settlements were generally small to insignificant in that area.
Reference points in the northwestern corner settled a little less than
0.4" whereas most other points in that area settled less than 0.2".
Reference points in the southern side showed the largest settlements during the
excavation progression. Near inclinometer I-70 a Boros anchor reference point
settled a little more than 1.0". The increase in settlement in that area
coincided with the maximum movements (towards the excavation 0.5")
recorded by I-70.
A gas main located near panel 75 showed significant settlement, with max
settlement of 1.3". Some small settlement occurred during the slurry wall
installation in that area 0.2" but there was a small slope failure at that
area due to improper trenching procedures (trenching without slurry). However,
it is not clear if these settlements should be considered as representative of
surface settlements because steel hangers supported the gas main.
Recorder settlements in the vicinity of panel I-83 were small, despite the fact
that panel 83 had the largest wall deflections in the project. However, this
may not be realistic since settlement monitoring in that area begun after the
excavation had progressed to some significant level (Midst Nov-1981). Slurry
wall settlements were recorded in panels 83 and 82a after that time (Nov-1981)
and showed a 0.2" max slurry wall settlement.
During slurry wall trenching problems arose with the guide walls since in many
instances guide walls pieces cracked and fell within the excavated trench. A
slope failure took place during trenching of a panel (panel 75) without slurry.
The slurry wall contractor had some difficulty maintaining the required slurry
levels that period in time. Slurry pockets were removed from completed panels
in two instances. Minor leaks through the panel jointing were observed and
easily patched with concrete. The slurry wall finish required occasionally that
the slurry wall contractor return and cut excess concrete pieces. Leaks were
also recorded in some tieback sleeve holes. At the final stages of the project
(near total completion) there were some cracks recorded in the upper garage
floor. Stress transfer from the slurry wall could have caused these cracks in
the garage floor.
Water levels outside the excavation were not significantly affected either by
the excavation or by the dewatering process. Overall, the slurry wall earth
support system performance was satisfactory. Settlement control was successful
in crucial areas and wall movements were typically small to moderate.

|