|
|
DEEP EXCAVATION CASE STUDY:
Rowes Wharf, Boston, MA
The
Rowes Wharf building is located on the easterly flank of Fort
Hill, one of the three original drumlins in Boston. The project
consists of a main 15-story building along with three wharf buildings
extending out over the water, and a 700-car five level underground
parking. A 2.5' thick, 65' deep, with 10' embedment perimeter
slurry wall. Rowes Wharf saw the introduction of Up/Down construction
in the northeastern U.S. (Becker & Haley, 1990). The included
figures show the plan, a typical cross section of the excavation,
and measured wall deflections of the project.
In addition to providing excavation support the slurry walls were designed to
reduce leakage and avoid excavation dewatering. A major issue that had to be
addressed was that the uplift pressure was greater than the building weight.
This problem was addressed by providing seepage cutoff with the diaphragm wall
extending below the excavation level into the glacial till. This allowed for
the lowest level floor to be designed as a fully relieved slab-on grade. Slurry
wall panels were typically constructed in alternate 20' sections
According to Haley (1986), wall movements were small. This project faced
serious problems with seepage through panel construction joints and through the
slurry wall itself. The slurry wall panel bottoms wall were not cleaned
adequately before concreting, and as a result waste material had accumulated at
the panel bottom. Concrete tremieing pushed part of this waste material to the
top of the slurry wall but a lot of that material got entrapped between panel
joints, and at the bottom corners of the slurry wall panels. These zones of
soft material leaked excessively when they where exposed by the excavation
activities. Major sealing efforts including grouting behind the wall and
filling with hydraulic cement were undertaken.
|