|
DEEP EXCAVATION CASE STUDY:
Millenium Place, Boston, MA
The
Millennium Place project includes a 55'-deep excavation with five
underground parking levels constructed by the up/down method.
The excavation has just been recently completed. Numerous buildings
are right next to the excavation along the northern, western,
and southern sides of the project. The MBTA Orange Line runs under
Washington Street to the east of the excavation. Thus, slurry
walls were selected to protect adjacent structures from excavation
induced damage. The figure on the left displays a typical excavation
section while the following figure shows the site plan.
Soils at the site are representative of profile B as classified by Johnson
1989. The soil profile consists of fill, organics, outwash deposits, marine
deposits, outwash deposits, glacial till, and bedrock.
The diaphragm walls are 3.0'-thick and have their toe embedded 40' beneath the
base of the excavation, into the marine and glacial till deposits. Load bearing
elements and caissons were constructed to carry the vertical loads from the
basement floors and the superstructure.
Measured wall deflections are in the order of 0.3" to 0.8" towards
the excavation, with some bending evident. Measured settlements are in the same
order as wall deflections but at some localized points settlements were larger
probably because of other construction activities.
|