|
A
reinforced concrete slurry wall was selected as the earth retention system for
the three-level basement. In addition, the 2-foot thick slurry wall was
theoretically able to carry wall loads in the order of 5 to 110 kips per foot.
The slurry wall penetration ranged from 58' to 90' below grade depending on
location (90' being adjacent to the University of Chicago Business School).
Immediately to the west of the site there is a 12 story high-rise structure
with a one level basement. This structure is the Knickerbocker Hotel located at
163 E. Walton Street. The low-rise structure south of the hotel was a one level
kitchen above ground, with a single mechanical room below. The University of
Chicago Business School is located to the west of the site at 190 E. Delaware.
The top/down slurry wall excavation at the Guest Quarters Hotel performed well.
Overall final wall deflections were in the order of dH=0.6" and only in
one point did they reached dW=1.0" . Caisson construction caused the
slurry walls to deflect by as much as 0.35" inwards, with typical induced
movements being smaller. Surprisingly, one inclinometer had the greatest
deflection of dW=0.97" in the cantilever phase when the first level of
excavation was reached (about 15' below street). Movements at that location a
sharply decreased to dW=0.5" when the second level slab was completed (24'
below street).
Other wall locations deflected up to dW=0.62" below the lowest slab level.
One of the inclinometers had its maximum deflection 8' feet below LL3 whereas
another had its maximum deflection at the LL3 level (34ft depth). It is clear
that the larger wall deflections below the excavation base are associated with
the soft to stiff silty clay, where the slurry walls were embedded.
Near a re-entrant corner, movements up to 0.56" in the primary direction
at the top of the slurry wall and up to 0.3" in the secondary direction
occurred at the final stage of the excavation. The combined primary and
secondary movement totaled 0.62" close to 30' below street level. This
suggests that both excavating faces affect movements near re-entrant corners.
There are no settlement data available, thus actual settlements are not known.
Settlements could be expected to be in the same magnitude or less than wall
movements if we consider that the top-down construction method was used.
The granular nature of the rubble fill caused problems in the guidewall
construction. Vibrations from the street caused some guidewall trenches to
collapse as they were excavated. This caused a section of the curb along Mies
Van der Rohe Way to slough into the excavation. It was decided to use soldier
piles and wood lagging on parts of the exterior slurry wall face as to avoid
this situation again.
Slurry leaked into a basement when panels were trenched in the northwestern
section of the project. The slurry leak into the Knickerbacker hotel occurred
about 12 ft below street level, where the retained soil consists of rubble fill
This demonstrates that running fills running (i.e. very permeable) may not be
able to form an adequate cake filter. Guidewall construction can be a little
problematic due to vibrations from street traffic. Street vibrations caused
soil collapses in this project required that the guidewalls were constructed to
a greater depth.
|