|
A principal concern in this project was the effects of excavating a 2-level
basement on the movements of the 10-story building on the east (Fig. 5.17). It
was felt that settlement of this building would be anticipated, regardless of
whether the building was underpinned or whether a stiff retention system was
adopted (Baker et al., 1987). A 30"-thick slurry wall constructed in 7' to
9' long panels was chosen on the east side of the project. On the other three
sides a 2' thick slurry wall was used constructed in normal 20' to 22' panel
lengths. The slurry wall extends from street grade at El. +14 ft CCD to
elevation El. -45ft CCD.
Three levels of rakers were used to support the east slurry wall. These rakers
rested on the caisson caps (Top Figure)). Raker installation was accomplished
with the use of soil berms along the east wall. Two inclinometers were
installed to monitor movements along the east wall. One inclinometer monitored
movements on the western side along Franklin Street where there was a major
sewer line.
Baker et al. [1989], report that slurry wall construction took place without
incident. Small concrete overpours in the order of 10% were typical during
slurry wall construction (archived information). Small movements, up to dH =
0.15" towards the excavation, occurred during slurry wall construction
(mostly observed below El. 0ft CCD along the eastern project side). Above El.
0ft CCD, soil moved slightly back by as much as 0.35" during slurry wall
construction. In the western side these movements were practically not
existent.
Caisson construction caused additional soil movements up to dH = 0.5" at
25' depth. When the first level of rakers was installed soil movements reached
close to dH = 1.15" along the east and dH = 0.5" along the west.
Final horizontal movements at the final stage reached dH = 1.5" along the
east and dH = 1.0" along the west (Bottom Fig.)). The added building
surcharge on the eastern wall was the cause of this difference in eastern and
western wall deflections.
Seventy percent (70%) of the total settlement occurred during the first level
raker installation. This settlement was close to dV = 0.09ft (dV = 1.08").
An additional 0.02ft settlement occurred when the 3rd level of rakers was
installed and removed. A total of dV = 0.11 ft of settlement is directly
attributed to the excavation and raker installation. When all the rakers were
removed settlements increased to a total of dV = 0.13ft (dV = 1.56").
.

|