|
|
DIAPHRAGM WALL CASE STUDY #3:
Washington Convention Center, Washington, DC
The Washington Convention Center project occupies five and one
half city blocks between Mt. Vernon Place NW on the south and
N Street on the north and from 7th Street NW on the east into
9th Street NW on the west, in Washington DC. The project is at
the present time the largest single basement slurry wall excavation
in the United States. The excavation site is approximately 1480'
long by 500' wide, and encompasses a 493,700 sq. ft. area. At
the north the excavation is 55' deep along N Street, but only
30' deep along the southern side.
Slurry wall
panels adjacent to the subway at 7th Street are 3.5'-thick, while
at all other location the wall thickness is 3.0'. This was done
in order to minimize the impact of the excavation on the adjacent
subway along 7th Street. The slurry
walls also provide water cut-off and thus minimize the dewatering
efforts that are required. Temporary bracing for this excavation
consists of a mix of tiebacks and prestressed rakers, depending
on location.
|
|
DEEP 2008 Software!!!

|
Subsurface conditions are typical of north central Washington
DC, combining a Pleistocene terrace deposit, over Cretaceous coastal
plain sediments, lying on a gently slopping bedrock surface at
a depth of 90' to 110' across the site.
Three levels of soil
tiebacks along the N-Street and the East alley brace the excavation.
Along other locations, one or two levels of tiebacks are used
in combination with a raker, and a raker heel block system. Adjacent
to tunnels, an upper level of tiebacks
and a lower level of rakers was used for temporary support. Two
levels of rakers and corner braces will be used at the re-entrant
corner where an entrance structure to the subway will be located.
The raker block is a concrete mass constructed into a depth of
16' below the excavation base, used for the rakers to transfer
the load. One level of tiebacks,
and rakers was used in most panels along Mt. Vernon Pl. NW. where
the excavation is approximately 30' deep. An additional level
of tiebacks was installed in deeper sections of the excavation.
The slurry wall
excavation at the Washington Convention center has performed well.
Conclusions about the overall performance can not be made because
the excavation has finished partially as of the last date when
data was available to us. The data in this report only cover up
to the completed excavation for the northern and southern project
sides. In addition, the accuracy of the available inclinometer
data is limited since readings were taken at 5ft intervals instead
of the regular 2ft, while none of the inclinometers extended beneath
the base of the slurry walls.
The largest slurry wall deflection, dH = 0.7", occurred
at the deepest section of the excavation along N Street, where
the wall was braced by three levels of tiebacks. This deflection
was not measured directly but it was reconstructed from data before
and after re-initialization of inclinometers took place. The wall
slightly bent only below the lowest tieback level, and above that
showed very little to no bending. Cantilever movements dominated
until the second tieback level was installed.
The largest horizontal soil movement, dH =0.75", occurred
at the southern side where the excavation was only 30' deep, braced
by an upper level of tiebacks and a lower level of rakers. The
corresponding wall deflection was not equal to the measured soil
deflection because the soil inclinometer extended deeper than
the base of the wall. This clearly shows the limitations of measured
accuracy when inclinometers lack reliable data. Unfortunately,
the inclinometers at that location were damaged before the excavation
was completed. Measured surface and building settlements were
too small and inconsistent to report on. The subway tunnels along
next to the excavation 7th Street did not show any significant
settlement.

|